Beaver Hills House Park and Michael Phair Park are being renewed. The second year of construction is underway.

Project update - May 2025

Due to the warmer weather, construction on Year 2 for Beaver Hills House Park and Michael Phair Park Renewal began sooner than expected. Construction started again in May 2025 and is expected to wrap up in fall 2025. 

During 2025, a number of construction activities will take place:

  • Site grading and paving stone installation throughout both park sites.
  • Installation of the new playground in Beaver Hills House Park.
  • Installation of a new pet relief area in Beaver Hills House Park.
  • Completion of the amphitheatre in the centre of Beaver Hills House Park.
  • Completion of the new washroom building in Beaver Hills House Park.
  • New artwork in Beaver Hills House Park.
  • Installation of the new bouldering wall in the northeast corner of Beaver Hills House Park.
  • Construction of the busking stage in Michael Phair Park.  
  • Completion of the Low Impact Development (soil cells) in the boulevard along 105 Street.
  • New site furniture, waste receptacles, bike racks and signage throughout both park sites.
  • Installation of lighting infrastructure throughout both park sites.
  • Installation of trees, shrubs, perennials, mulch, and sod throughout both park sites.

Please note, the pedestrian walkway along Jasper Avenue will be closed again during construction to allow for the removal of the temporary asphalt and the placement of the new paving stones. The pedestrian walkway along 105 Street will remain closed until late summer 2025. The east lane of 105 Street will close for a short period of time in June. Please follow all signage and crew direction in this active construction space.