Project Update - Fall 2024
Construction of Coronation Park Sports and Recreation Centre continues. The project is on time and on budget, and is anticipated to be complete in 2026.
The building’s exterior is nearing completion as work on its major structural steel is complete and the concrete is almost complete. Work continues on the building’s roof and the connection to Peter Hemingway Aquatic Centre.
Inside the building, structural concrete work is complete. All rooms are framed, drywalled tiled and are being painted. Work on the ceilings throughout the facility continues. The facility’s mechanical and electrical systems are progressing, some of which are already going through start-up procedures.
The structure of the cycling track has been completed. Preparations continue ahead of the installation of the cycling track.
Outside of the facility, work has begun on the landscaping, curbs, sidewalks, roadways and parking lot.