This year, work on the Fort Road Widening Project focused on completing the CN bridge over Fort Road and removing the temporary bridge detours. With trains operating on the new structure since the middle of July, construction activity has been progressing towards completing the majority of work by the end of 2023, with some carryover work expected for 2024.
On October 30, Fort Road reopened to reduced capacity with 1 lane of traffic for travel in both directions. As construction continues, we plan to gradually reopen more lanes of traffic throughout 2023 and into early 2024, along with pedestrian and active mode access.