Rehabilitation work on the Beverly Bridge is underway. This project will extend the bridge’s lifespan and improve safety for all users.

Project Update -November 2025

Rehabilitation work on the Beverly Bridge is underway. Rehabilitation will take approximately two construction seasons and is expected to be completed by the end of 2026. Construction work will be done in two phases to minimize traffic impacts. 

Stage 1 began in 2025 on the south side of the bridge. Construction was completed in November 2025 and included:

  • Concrete bridge deck repair
  • Waterproofing
  • Deck paving
  • Bridge girder, bearing and abutment repair
  • Upgraded street lighting 

The bridge has now reopened to 3 lanes of traffic for the winter season.

Stage 2 starts in 2026 and includes work on the north side of the bridge. The bridge will be temporarily reduced to two lanes while this work is underway. Pedestrian access to the trail under the bridge will remain open during construction. To ensure the safety of pedestrians, hoarding will be installed during overhead work.
 

Project Area: Beverly Bridge Rehabilitation

Project Timeline

Project lifecycle build image

2025

  • Construction anticipated to begin (Stage 1)

2026

  • Construction to continue (Stage 2)

Project History

Project Information

Rehabilitation construction on the Beverly Bridge will begin in 2025 to extend its life and enhance safety. The rehabilitation will include repairs to the concrete deck and steel girders, new pavement and traffic barriers, and miscellaneous other minor repair work on the bridge and approach roadway.

As part of the project:

  • The bridge will be reduced to two lanes during construction, which is planned to take place from spring 2025 to fall 2026.
  • The work will be completed in two stages with Stage 1 occurring in 2025 and Stage 2 in 2026.
  • It is expected that the bridge will be reopened to three lanes of traffic over the 2025/2026 winter