About the Project
As part of the development of the Horse Hills Neighbourhood, private developers are required to upgrade Meridian Street from a rural road to the first two lanes of urbanized arterial roadway.
This project will also require the construction of a new culvert and a wildlife passage at the Horsehills Creek crossing.
As the project will require a year-long closure of Meridian Street from 167 Ave to the CN rail tracks, a traffic detour plan has been created to ensure residents have access to their homes in the area.
Read the
Meridian Street Developer Road Construction Brochure
for complete details of the project.
Revised Project Timeline
Spring-Summer 2022: 167 Avenue WB at Meridian Street closed
August 2022: Meridian Street re-open to traffic
Summer 2023: Meridian Street construction to continue, additional lane closures expected
Developer |
Engineer |
---|
Qualico Communities
780-463-1126
|
WSP
|
MLC Group
780-420-0044
|
WSP |