Base inspection costs are included in permit fees. See Additional Fees for more information on costs for additional inspections.
Fees listed below apply to both stand-alone HVAC permits and HVAC permits obtained in connection with a building permit.
New Construction
2024 fees effective January 1, 2024
Project Type | HVAC Permit Fee | Minimum Fee | Safety Codes Fee |
New commercial, industrial, institutional, multi-residential development | $0.58 per $1,000 construction value | $180 | 4% of the permit cost with a minimum of $4.50 and maximum of $560 |
Altering or Replacing an Existing System
2024 fees effective January 1, 2024
Project Type | HVAC Permit Fee | Safety Codes Fee1 | Total |
Commercial building | $180 per unit or address | $7.20 | $187.20 per unit or address |
Multi-unit residential building | $115 per unit or address | $4.60 | $119.60 per unit or address |
(1) Construction value is defined as the total cost of materials and services. Construction value does not include: landscaping, parking lots, sidewalks, furnishings, appliances, interior window coverings, temporary service connections, insurance or bonding, interim financing, permit fees, professional consulting fees, GST.
(2) Safety code fee is 4% of the permit cost with a minimum of $4.50 and a maximum of $560.00.
For more information see the 2024 Planning and Development Fee Schedules , effective January 1, 2024.