Base inspection costs are included in permit fees. See Additional Fees for more information on costs for additional inspections.
Stand-Alone Electrical Permits
2024 Fees (effective January 1, 2024)
For stand-alone fee estimates see the
2024 Electrical Permit Fee Estimator
.
Electrical Permits Obtained In Connection with Building Permit
2024 Fees (effective January 1, 2024)
Construction Value 1 |
Base Fee |
Safety Codes Fee |
$0 - $24,000 |
$155 |
4% of the permit cost with a minimum of $4.50 and a maximum of $560.
|
$24,001 - $80,000 |
$220 |
$80,001 - $400,000 |
$390 |
$400,001 - $2,000,000 |
$800 |
$2,000,001 or greater |
$2,585 |
1 Construction value is defined as the total cost of materials and services. Construction value does not include: landscaping, parking lots, sidewalks, furnishings, appliances, interior window coverings, temporary service connections, insurance or bonding, interim financing, permit fees, professional consulting fees, GST.
Annual Permits
2024 Fees (effective January 1, 2024)
Permit Fee
Base Fee |
Multiplier |
$330 |
$1.10 per $100 of electrical installation cost 1 |
1 Electrical installation cost is the total amount of materials and labour.
Inspection Fee
2024 Fees (effective January 1, 2024)
Inspection Fee |
Safety Code Fee 1 |
Total |
$155 per hour (minimum 1 hour fee)
|
$6.20 |
$161.20 per hour |
Note: The Safety code fee is 4% of the permit cost with a minimum of $4.50 and a maximum of $560.
For more information see the
2024 Planning and Development Fee Schedules
, effective January 1, 2024.