Construction Update - November 2025
Neighbourhood Renewal construction in Overlanders has wrapped up for the 2025 construction season!
2025 construction began in May and was finished the 3rd week of October. The 2025 construction season was a success and we completed all planned construction including:
The reconstruction of roads, sidewalks, curbs and gutters in the following areas:
- William Hustler Cresent
- Humberstone Road
- Hunt Road
- Huffman Crescent
- Hughes Road
Streetlights in the 2025 construction area were not completed this year. Crews will replace the lights over the winter.
Parts of the 2025 construction area may also require sod. Once the weather warms up, typically in early May, the landscape subcontractor will be completing the sod placement. By waiting until spring, the sod is more likely to establish.
Neighbourhood Renewal work will resume in Overlanders in spring 2026, weather permitting. The planned scope for 2025 will include Hooke Road, Hollinger Close, Horner Road and Hooper Crescent. Prior to work resuming, construction notifications will be delivered to impacted residences.
Thank you for your patience and understanding as we completed another successful year of Neighbourhood Renewal construction. Construction in Overlanders began in spring 2025 and is expected to take 2 years (planned completion fall 2026).
Neighbourhood renewal in Overlanders is progressing on time and on budget.
Check out the links below to prepare for construction:
Construction in Overlanders began in spring 2025 and is expected to take 2 years (planned completion fall 2026).