Construction Update - October 2025
The third year of Ottewell Neighborhood Renewal construction is underway! Work will consist of removal and replacement of sidewalks, curbs, gutters and street lights as well as reconstruction and paving of the roads and all associated landscaping.
The 2025 Ottewell neighbourhood renewal project is nearing completion, with the construction of sidewalks, drainage, and Low Impact Development (LID) structures progressing significantly. Streetlight installations are also progressing as planned.
Please find below the details for the upcoming road closures, which are subject to weather conditions:
- 95 Avenue east of 67A Street: Paving completion is tentatively scheduled for the first week of October
- 58 Street between 92A Avenue and 91 Avenue: Paving completion is tentatively scheduled for the second week of October.
- 94A Avenue: Paving completion is tentatively scheduled for the second week of October.
- 95 Avenue west of 67A Street: Paving completion is tentatively scheduled for the first week of October.
- 67A Street: Paving completion is tentatively scheduled for the first week of October.
For those who live in the 2024 construction area along Ottewell Road (from 94 B Avenue NW to 94 Avenue NW), the timeline for the remaining work depends on the scope of EPCOR’s sewer separation project. Since construction is weather-dependent, EPCOR work is set to resume in May 2025. The City is coordinating with EPCOR to prioritize the construction schedule for the remaining work along Ottewell Road.
Review the final design for remaining construction
Thank you for your continued patience and support as we work to finalize the 2025 Ottewell neighbourhood project.
Construction in Ottewell began in spring 2023 and is expected to take 5 years (planned completion fall 2027).