October 2025
Please find below the details for the upcoming road closures, which are subject to weather conditions:
- 95 Avenue east of 67A Street: Paving completion is tentatively scheduled for the first week of October
- 58 Street between 92A Avenue and 91 Avenue: Paving completion is tentatively scheduled for the second week of October.
- 94A Avenue: Paving completion is tentatively scheduled for the second week of October.
- 95 Avenue west of 67A Street: Paving completion is tentatively scheduled for the first week of October.
- 67A Street: Paving completion is tentatively scheduled for the first week of October.
September 2025
Drainage infrastructure work, including Low Impact Development (LID) structures, is well underway. Sidewalk installation near the LID facilities is progressing, and the backfill of the LIDs is proceeding ahead of road rehabilitation. Street light installations are progressing. The contractor is positioning new street lights as close to property lines as possible.
Upcoming road closures (Please note, all timelines may change, depending on weather conditions):
- Until September 27: 68A Street, 94B Avenue and 68 Street
- After September 27: 95 Avenue (east of 67A Street), 68A Street continuing to 96A Avenue and the 98 Avenue service road (west of 64 Street)
August 2025
Sidewalk installation near the LID facilities is progressing. The backfill of the LIDs is proceeding sequentially in anticipation of road rehabilitation. Drainage infrastructure work, including Low Impact Development (LID) structures, is well underway.
Street light installations are also progressing. The contractor is working to position new street lights as close to property lines as feasible.
Weather permitting, community members can expect the following road closures:
- Ottewell Road will be closed from August 7 to August 22 for road rehabilitation. Access to residences will be available via the back alley
- 94B Avenue and Ottewell Road will be closed August 23 to August 25 for concrete raised intersection construction
- Road Rehabilitation from approximately 7am to 8:30pm August 11 to August 22:
- 68A Street from 94A Avenue to 94B Avenue
- 95 Avenue, 68 Street to 69A Street
July 2025
Sidewalk installation has started on 95 Avenue, east of 69 A Street and the Braemar School area. Drainage infrastructure work, including Low Impact Development structures, is underway across the project area.
Street light relocation and installation is anticipated to begin in early July, starting on 94 B Avenue and Braemar School area.
Work and road closures are currently ongoing at the following locations:
- Road work on the intersection between Ottewell Road and 94 B Avenue, and Ottewell Road south of 94 B Avenue to 94 Avenue NW
- Road rehabilitation starts on the second week of July, along 67 A Street, 68 A Street, 94 Avenue, 94 A Avenue
- Road rehabilitation on 94 B Avenue, then move on to 97 Avenue
Please note, EPCOR Drainage is currently installing the drainage facility along Austin O'Brien Rd NW.
Additionally, the Phase 1 work along 91 Avenue and 58 Street that was deferred due to EPCOR drainage work is now under construction.
June 2025
Sidewalk installation has started on 94B Avenue, starting just east of Ottewell Road. Drainage infrastructure work is underway across the project area.
We anticipate street light relocation and installation to begin in early June, starting on 94B Avenue.
Work is currently ongoing at the following locations:
- 94B Avenue, from Ottewell Road to east of 68 Street
- 69A Street, from 95 Avenue to 97 Avenue
- 97 Avenue, around the pocket park
- 98 Avenue service road, from Ottewell Road to 64 Street
- 64 Street, from 97 Avenue to 98 Avenue
Please note that EPCOR Drainage is currently installing the drainage facility along Ottewell Road from 95 Avenue to 96A Avenue. The road is temporarily closed to vehicle traffic in this section.
98 Avenue is reduced to single lane traffic eastbound starting May 26 from 9am to 3pm until the work is completed.
Additionally, the Phase 1 work along 91 Avenue and 58 Street that was deferred due to EPCOR drainage work is scheduled to resume in June 2025.