Hyundai Rotem Company will supply 46 new low-floor LRVs for the Valley Line West project. Design review work was completed in 2024. The first LRV was delivered to Edmonton in summer 2025. These LRVs will be compatible with, and incorporated into, the entire Valley Line fleet.

The first Valley Line West Light Rail Vehicle being loaded on a cargo ship in south Korea

The first Valley Line West Light Rail Vehicle was loaded on a cargo ship in South Korea earlier this summer. It has arrived in Edmonton.

Photo courtesy of Hyundai Rotem Company

May 2025 Update

The first Valley Line West Light Rail Vehicle (LRV) is scheduled to arrive in Edmonton by summer 2025, following months of rigorous testing in South Korea. This includes low-speed dynamic testing, systems validation and a final inspection.

Additional vehicles in the 46-LRV fleet are in various stages of assembly and testing.

July 2024 Update

As of mid-2024, Valley Line West LRV development remained in the final design phase, with significant progress toward manufacturing.

Throughout the year, Hyundai Rotem and the City of Edmonton finalized key design elements and began component testing. This included motor, braking and climate-system testing to ensure the LRVs can operate safely and comfortably in Edmonton’s extreme weather conditions, from -40C winters to 40C summers.

Manufacturing of full vehicle modules began later that year.

June 2023 Update

In early 2023, the City invited Edmontonians to test a full-scale mock-up of the new Valley Line West Light Rail Vehicle (LRV). The mock-up included about a quarter of the train, featuring the cab and a passenger area with an accessible wheelchair space. Built from wood and fibreglass, the model allowed people with a range of mobility needs to interact with the design, testing doors, seating layouts and accessibility features like wheelchair spaces and tactile push buttons.

Feedback helped improve the vehicle’s design to ensure it’s accessible, comfortable and inclusive for all Edmontonians.

Design work with Hyundai Rotem Company continued through 2023, with vehicle production scheduled to begin in 2024.

Watch the video

November 2021 Update

In November 2021, the City of Edmonton selected Hyundai Rotem Company as its preferred proponent to supply light-rail vehicles (LRVs) for the Valley Line West. Read our news release for more information on the award of the LRV contract.

March 2021 Update

The request for qualifications (RFQ) closed on February 4, 2021. On March 4, 2021, the City shortlisted 3 teams to participate in the Request for Proposal (RFP) phase of LRV procurement. Please read our industry bulletin for more details.

November 2020 Update

The project entered into Light Rail Vehicle (LRV) procurement on November 24, 2020 (see industry bulletin).