Project Update - Spring 2025
Construction is underway to alleviate congestion, accommodate current and planned transit services, and enhance existing active transportation connections to provide all users with a safe and efficient route. Stage two construction will continue through 2025 and is anticipated to be completed in 2026.
Construction details:
- Girder and bridge deck installation for the eastbound Rainbow Valley Bridge, the Rainbow Valley Pedestrian Bridge and the 142 Street Pedestrian/Cyclist Bridge.
- Completion of the westbound Rainbow Valley Bridge and traffic pattern shift to the completed bridge to accommodate construction work on the eastbound Rainbow Valley Bridge.
- Bus lane construction from 53 Avenue to Terwillegar Drive and completion of the supporting retaining wall.
- Widening of Whitemud Drive eastbound between 53 Avenue and 122 Street.
During construction, Whitemud Drive will have two lanes open in each direction during peak hours.