Project Update - Fall 2025
Through the summer construction season, Ledcor continued to make progress on the pedway project. This included adding mechanical, electrical and architectural elements to the tunnel section north of 103A Avenue and completing all excavation and concrete slab pours in the future “pop-up” located near the CN Tower bus loop.
Another achievement this summer was the successful switch of the construction site where work was moved from the south to the north section of 99 Street. The roadway and sidewalk on the south half of 99 street has been fully reinstated while work continues underground in the new tunnel. This major milestone also means that the project has entered its final phase of excavation work. To allow for this work to occur, City Hall parkade access will be via 102A Avenue only and will no longer be available off 103A Avenue, which is highlighted in our project update.
More information can be found in our updated phasing plan for impacts on pedestrian, bicycle and vehicular traffic.