Construction Update - November 2023
2023 construction began in May and was finished the second week of October. The 2023 construction season was a success and we completed all planned construction including:
- The reconstruction of alleys, shared streets and shared use paths, in the following areas:
- Alley south of 46 Avenue between 117A Street to Malmo Road
Parts of the 2023 construction area may also require sod. Once the weather warms up, typically in early May, the landscape subcontractor will be completing the topsoil and sod placement. By waiting until spring, the sod is more likely to establish.
Neighbourhood renewal work will resume in Malmo Plains Neighbourhood in the first week of June 2024. The planned scope for 2024 will include sod placement only.
Thank you for your patience and understanding as we completed Neighbourhood and Alley Renewal construction in Malmo Plains!