Construction Update - June 2025
The second year of Hairsine Neighbourhood Renewal is underway. Work will consist of reconstruction and paving of the roads, removal and replacement of public sidewalk, curb, gutter and street lighting, and park lighting.
At this time, construction is being done on the northwest outer loop and on the north side of the long cul-de-sac of 142 Avenue. Next, crews will move to the west side of 36 Street and the northeast inner loop.
Construction has begun in Hairsine Park for new trails, seating areas and landscaping. That work will continue until the fall. Planting and sod is ongoing south of 139 Avenue and along 36 Street.
This year, the majority of construction will take place from West of Victoria Trail to 36 Street between 139 Avenue and 144 Avenue. Please view this scope map to see the 2025 construction area. Work will also happen in the Hairsine Park.
Parts of the 2024 construction area may also require sod. Once the weather warms up, typically in early May, the landscape subcontractor will be completing the topsoil and sod placement.
For those who live in the 2025 construction area, the landscaping work is scheduled to start after installation of new concrete sidewalks. Landscaping work is highly dependent on weather and sod availability.
Check out the What We Decided report to learn more about Hairsine Neighbourhood Renewal.
The City of Edmonton and EPCOR are working together to construct Low Impact Development (LID), which will help with stormwater retention and help mitigate flooding.
Please watch your mailbox for construction bulletins that will provide more information along with details on landscaping and access. All residents and business owners are asked to access their homes and businesses through the back entrances and alleys, where possible, during construction. If no alley access is available and/or you have special access requirements (such as DATS or a temporary access ramp to the front of your home), please contact the Construction Project Manager, Sharad Dhakal, sharad.dhakal@edmonton.ca, phone number 780-496-4055, to coordinate.
Construction in Hairsine began in 2024 and is expected to take 2 years (planned completion 2025). Neighbourhood renewal in Hairsine is progressing on time and on budget.