Surface Asphalt Repair Process
Step 1: Grinding Phase
This stage typically lasts 3-5 days as crews utilize heavy equipment to remove the surface levels of defective asphalt. 'No Parking' signs and Road Closures will be in place. Following completion of this step, a break of 1-2 weeks will occur. During this break, normal driving and parking conditions resume.
Step 2: Paving Phase
This process usually spans 3-5 days as crews replace the defective asphalt with new material using heavy equipment. 'No Parking' signs and Road Closures will be enforced. After paving is finished, normal driving and parking activities resume until the subsequent phase.
Step 3: Leveling Stage
Approximately 1-2 weeks after paving, crews return to adjust existing utilities such as manholes and valve vaults to ensure the new surface is level. Parking will only be affected around each utility item for a day or two.