Construction Completion Certificate:

Once the municipal improvements have been constructed, the developer's consultant must request an inspection for each municipal improvement, and submit any required test results and backup documentation, in order to process the Construction Completion Certificate (CCC) request, as outlined in the servicing agreement.

Process Changes

Effective March 31, 2016, the CCC process is managed, including submission of inspection requests, using the eServices portal.

Submit a request

For more information, contact Development Coordination

City Groups and External Agencies

The following City groups and external agencies are responsible for the corresponding improvements:

Development Inspections

  • Paved roads, sidewalks, curb and gutter
  • Walkways
  • Paved alleys
  • Street lighting system
  • Temporary turnarounds
  • Temporary emergency accesses
  • Fencing
  • Landscaping
  • Landscape Amenities

Drainage Services 

  • Storm and sanitary sewers and service connections
  • Grass and concrete drainage swales
  • Storm water management facilities
  • Sanitary lift stations
  • Temporary drainage features

Epcor Water Services Inc

Water system and service connections

Epcor Distribution Inc

Electrical distribution system

Final Acceptance Certificate

Upon expiry of the maintenance period of each municipal improvement outlined in the servicing agreement, the developer's consultant must request an inspection for each municipal improvement, and submit any required test results and backup documentation, in order to process the Final Acceptance Certificate (FAC) request.

The purpose of the FAC is to transfer full responsibility for a municipal improvement from the developer to the City. 

Process Changes

Effective March 31, 2016, the FAC process is managed, including submission of inspection requests, using the eServices portal.

Submit a request

For more information, contact Development Coordination