The Kinnaird Bridge, located on 82 Street, south of 112 Avenue and north of 111 Avenue, will be rehabilitated. Construction is anticipated to begin May 2023.

Project Update - June 2022

Detailed design for the bridge rehabilitation is complete. Construction on the Kinnaird Bridge is anticipated to begin spring 2023.

Construction details:

  • Bridge deck, sidewalk, and barrier repairs
  • Approach slab upgrades
  • Re-grading under bridge
  • Painting bottom of piers and sidewalk supports
  • Landscaping: tree and shrub restoration and soil clean-up

One lane of traffic in both directions and one sidewalk will remain open at all times, where possible. Alternative routes for pedestrians, cyclists, motorists and transit will be shared closure to construction dates.  

Thank you to those who attended either of our information sessions on June 15 and June 16 to learn about the upcoming construction plans!

Information Session Presentation - June 2022

About the Project

Kinnaird Bridge was originally constructed in 1932 and currently serves as an arterial roadway with 4 lanes of traffic. Kinnaird Bridge is located along 82 Street, south of 112 Avenue and north of 111 Avenue.

The bridge crosses Rat Creek, which features a mixed use trail providing further access to Rat Creek trails and the river valley.

A Condition Assessment and Preliminary Rehabilitation Strategy Report was completed in August 2019 for Kinnaird Bridge and recommended minor rehabilitation.